CHARTERED SEMICONDUCTOR MFG LTD
(Now Known as Global Foundries)

CSM EXPANSION - WOODLANDS

  • Chemical drains from proposed clean room to chemical storage tanks at lift station (MAR – MAY 2000)
  • Supply, fabricate & install equipment foundation (Since 1999)
  • Supply, fabricate & installation of Process Cooling Water (PCW) pipes at Centralized Implanter Room (APR 2000)

CSM EXPANSION - WOODLANDS

  • Installation of double containment for chemical line and electro-polished tubing.

CSM EXPANSION - WOODLANDS

  • Supply, fabricate & install for photo resist cabinet & sub-main piping (NOV 1999 / JAN 2000)
  • Design the piping layout and install all drain systems (e.g. IWW, HF, IPA, etc). (Class 100 Clean room)
  • Supply and install Equipment Foundation ID : Stepper – A31(JUL 2006)

CSM FAB 7 – WOODLANDS

  • ProcessWater System, Process Cooling Water System, Process Vacuum System, House Cleaning Vacuum System. & Chemical Drains System (MAR – MAY 2000)
  • Supply, fabricate & installation of Chemical Drains System (JUL 2000 / JUN 2001)
  • Supply, fabricate & installation of Process Cooling Water, ProcessWater Systems (JUL 2000 / JUN 2001)
  • Supply & install 9K Equipment foundation bases (NOV 2000 / JUN 2001)
  • F43A Expansion works (Phase 1) – New drain systems and relocation of existing drain system (JUN 2002 / OCT 2002)
  • F43B Fab. 7 PCW Expansion (JUN 2002 / OCT 2002)
    • Critical system expansion (Sub-fab. PCW & PCWS modification)
    • Upgrading of Sub-fab. PCW Sub main piping and to upgrade 2 nos. of PCW heat exchangers.
      • Supply and install SS304 Sch. 10 pipe and fittings at CWCR & PCWCS 15° Fab. 7 (JUN 2006)
      • Supply and install partition at DIWater Plant & Dismantle of 4 nos. CDI skids at DIWater Plant (JUL 2006)
      • Conversion of part of existing slurry treatment room to mixed solvent waste room (NOV 2008)

CHARTERED SILICON PARTNERS PTE LTD

CSP – WOODLANDS

  • Supply, fabricate & install equipment foundation (1999 / 2000)
  • Installation of DI water piping – to install UPW Loop CUB Area Expansion at CSP (15K onward UPW Loop) (AUG 2002 / SEP 2002)
  • Process Water Tank (APR 2006)
  • Supply and install SS304L pipe & fittings for Solvent Drain Line @ Sub Fab., Location Bay 8 (JUN 2006)

CSP F43A – WOODLANDS

  • Additional chemical drain lines (PVDF & PP Material) (OCT 1999 / FEB 2000)

CSP F43B - WOODLANDS

  • Supply & install for Emergency eye shower & water supply pipes. (NOV 1999 / MAR 2000)

3COM & Taiji Network Co., Beijing CHINA

Turnkey for Mechanical and Electrical engineering works, including HVAC, waste water treatment and water supply
systems, building renovation work, fire alarm and security systems

  • Electrical engineering system design, drawing, supply, installation, testing and commissioning (main power incoming: 1200A/TP).
  • Electrical panels fabrication, installation, testing and commissioning.
  • HVAC and M&E systems design, installation, testing and commissioning.
  • Fire alarm and security systems design, installation, testing and commissioning.
  • Supply, fabricate and installation of Waste water treatment and water supply systems.
  • Building renovation work. (JAN – APR 2000)

3M SINGAPORE PTE LTD – Woodlands

HOOK UP

  • Fabricate, supply & installation of condenser water, compressed air, process & high/low pressure piping systems.
  • SS pipe-rack for equipment, SS plates for clean room, Double Containment Pans, Mechanical catwalk
  • Installation of AHUs
  • Structural steel works
  • Chemical Drains System.

ELECTRICAL & CONTROLS WORK

For Chem. Mill #2, Flash Platter #2, Wide Web Clean #2, Chemical (H2O2) Container Level Monitoring System

  • Supply and lay incoming power cables (4x240mm sq. + PE, XLPE).
  • Supply and install cable ladder, tray, trunking and supports.
  • Instrumentation system installation.
  • Electrical and control system design and drawings (non contact level monitor system).
  • Electrical panel fabrication and installation. Cabling, wiring and site commissioning.

MECHANICAL & ELECTRICAL INSTALLATION

  • For Chem. Mill #4
  • Mino Screen Printer
  • Lexmark Cover coat Oven

TECH SEMICONDUCTOR (S) PTE LTD

TECH PHASE 1 & 2 (Class 1 Cleanroom)

  • Design the piping layout for the PCW system and Plant vacuum system in the Mech. Wing including the pump inertia block and supports.
  • Install all PCW equipment, i.e. : heat exchanger, pumps, filters & PCW tank and all inter-connecting piping.
  • Design the piping layout and install all drain systems in both FAB building and Mech.
    e.g. : IWW, HF, IPA, etc
  • Wing Equipment hookup for the following services: – PCW, IWW, HF, Solvent, Plant vacuum, brackets.

DUPONT PHOTOMASK (S) PTE LTD

  • Equipment Foundations and fabricate support base for steppers, implanters, SEM and KLA.
  • PCW and bracket supports

SILICON MANUFACTURING PARTNERS

SMP - WOODLANDS

  • Supply, fabricate & install equipment foundation (1999 / 2000)

DAIKEN ENGINEERING

TOSHIBA AFPD LCD FACTORY

Supply and install GI Hollow section partition frame and two layers of Gypsum board at 1st Main 3rd Cell (AUG 2006)

HITACHI –NIPPON STEEL SEMICONDUCTOR SINGAPORE PTE LTD

HOOK UP (Class 10 Clean room, 12000 sq m)

  • Installation of Filter and Fan Filter Units .
  • Process Cooling Water System, Plant Vacuum System, Waste Water System, Ultra Pure Water System. (NOV 1999 – MAR 2000)

IBM @ KAKI BUKIT

Class 10 Clean room, 10800 SqM

  • Installation of clean room ceiling.
  • Installation of Filter and Fan Filter Units.
  • Certification of clean room.

INSTITUTE OF MICROELECTRONICS

IME

  • Equipment Foundations and Piping Hook-up.

GE BETZ SINGAPORE PTE LTD

SEAGATE @ WOODLANDS

  • Supply & install piping for DI S&R system, drain system, for RO, DI & WWTP systems at CUB and SAC tanks & polishing mixed bed tanks (DEC 2003 / APR 2004)
  • Electrical works for waste water treatment (FEB 2004 / APR 2004)
  • Mechanical (UPW plant room) & Electrical and control works for PHASE 2 (FEB 2005 / JUL 2005)
  • Mechanical works for Seagate PHASE 2 drainage piping (FEB 2005 / MAY 2005)
  • Mechanical (UPW plant room) & Electrical and control works for PHASE 3 (SEP 2005 / FEB 2006)
  • Supply and installation of UPW Distribution Loop and Drainage System for PHASE 3 (OCT 2005 / FEB 2006)
  • Hook Up Piping Work For UPW and Drain for PHASE 3 (JAN 2006 / MAR 2006)
  • UPW Plant Room & Supply and install UPW distribution loop, drain and hook up for clean room level 4, Mechanical contractor for RODI, AWN and Reclaim Plant for PHASE 4 (AUG 2007)

GLOW (THAILAND)

  • RO PLANT (DEC 2005 / MAR 2006)

CHRIST WATER SINGAPORE PTE LTD

SILTRONICS

  • Package #1 CUB, Chemical area installation and preliminaries (OCT 2007)

IMFS – 50058 (UPW)

  • UPW Plant CUB Area (AUG 2008)

SHANGHAI BELLING MICROELECTRONICS MFG CO LTD - CHINA

FAB PRODUCTION AREA (Class 10 Clean room)

  • Installation of exhaust for chemical cabinet (PVC 8” pipe).
  • Installation of process nitrogen line SS 316 1” and ½” pipe.
  • Installation of clean dry air line SS 316 1” and ½” pipe.
  • Installation of city water pipe line – UPVC 2” and 1” pipe.

SHIN NIPPON AIR TECHNOLOGIES

AFPD’S LCD FACTORY - TAMPINES IND. AVE 3 / TAMPINES AVE 10

  • Pipe work installation for Toshiba Factory – Process piping and A/C drain piping (Phase 1) (AUG 2001 / JAN 2002)
  • Supply labour and materials for Clean room cleaning (Phase 1) for AFPD’s LCD factory (DEC 2001 / MAR 2002)
  • Piping systems & exhaust systems hook-up to manufacture machines in the FAB for AFPD’s LCD factory (FEB 2002 / JUN 2002)

BSK MEMBRANE PTE LTD

WOODLANDS VISTA POINT

  • Installation of tension membrane steel structure c/w fabric membrane installation (2011)

PUNGGOL

  • Installation of tensile membrane (2011)

JURONG ENTERTAINMENT CENTRE

  • Hoisting and installation of tensile membrane (FEB 2012)

IM FLASH SINGAPORE

IM FLASH

  • Maintenance Contract for Pumps (FEB 2012)

MICRON SEMICONDUCTOR ASIA PTE. LTD.

MICRON

  • Maintenance Contract for Pumps (FEB 2013)
  • Maintenance Contract for Pumps (FEB 2014)

Micron Fab 10X-F21

  • Fab 10X April Funding CDA7-Utilities Connection to Equipment

Micron Fab 10X

  • Sampling Sump & New Penstock Sewer Line
  • UPW Plant

Micron Fab 10N

  • Cooling Water Closed Loop for CDS System

Micron Fab 10A-F08F

  • AMHS Linkbridge (LA1 West & LA2 East) – F08F Chilled Water Piping Works (Both West and East Bridge)

SINGAPORE PRESS HOLDINGS – JURONG PRINT CENTRE

  • Contract for monthly preventive maintenance ACMV (JUN 2003 – SEP 2009)
  • Contract for monthly preventive maintenance ACMV (JUN 2009 – MAY 2010)
  • Preventive Maintenance for 2 years contract (JUN 2009-MAY 2011)
  • Replacement of new bearing & shaft at PC1 L2 EAF 2-4 (2011)
  • To replace CARRIER fan coil unit at PC1, Level 2 Pantry Room (2011)
  • PC2 Cooling Tower (6nos) internal structure replacement, painting of chilled/ condensing water/drain pipe & reinforced basin (2011)
    Contract for monthly preventive maintenance ACMV (JUN 2011 – SEP 2012)
  • Contract for monthly preventive maintenance ACMV (OCT 2012 – JUN 2013)
  • Contract for monthly preventive maintenance ACMV (JULY 2013 – JUN 2014)

RENEWABLE ENERGY CORPORATION (REC)

  • Installation of Temporary pipe line from Fire Hydrant point at 4J & 4N East to the supporting areas of 2F, 4M & 4L Bldg
  • To install CDA piping at Module Level 3 Production Area (2011)

M+W ZANDER PTE LTD

SSMC – PASIR RIS

  • Supply, fabricate & installation of Equipment Foundation from 5K to 30K (APR 2000 / JUN 2002)
  • Hook Up 30K Project -> Equipment Foundations & Mechanical Piping (JUN 2002 / OCT 2002)
  • Hook Up 33K & 40K -> Supply & install materials for equipment foundation for phase 1 (33K) & Phase 2 (40K) (PHASE 1 – JUL 2004 / DEC 2004 & PHASE 2 – JAN 2005 / DEC 2005)
  • Hook Up 33K & 40K -> Supply & install materials for mechanical piping (HK43B/D) for phase 1 (33K) & Phase 2 (40K) (PHASE 1 – JUL 2004 / DEC 2004 & PHASE 2 – JAN 2005 / DEC 2005)
  • Hook Up 33K & 40K -> Supply & install materials for drain system (HK43A) for phase 1 (33K) & Phase 2 (40K) (PHASE 1 – JUL 2004 / DEC 2004 & PHASE 2 – JAN 2005 / DEC 2005)
  • Waste Water Treatment Process Piping Works  To supply and install for additional BGW/MPW transfer system & modification for balance pipe of BGW/CMPW lift tank.
  • PCW & PV system relocation for RA Lab, Supply, install and modify of PCW system take-off valve for FA lab.
  • Supply & install of sub-main lines for PCW, PV, RW & Drain system at Copper South Side Room.
  • AWD Drains – Hookup to Southside scrubbers including sub mains & mains to CUB
  • 45K Hook up for Mech piping (PCW,RW,PV), UPW, Drains, Equipment Foundation and other additional works.
  • Equipment Hook Up for ACVA05(PCW, RW, AWD), ACV717(PCW, RW, PV, AWD and SS Plate), ACH310(PCW, RW, AWD and SS Plate), AIM201 (Mech piping & Steel foundation)
  • Temporary Process Cooling Water Supply (MAY 2007)

UMC – Pasir Ris

  • Supply & install tools foundation @ UMC

MSD

  • New pharmaceutical facilities (NPF) project at Tuas – F43 Chemical Sewer Systems (NOV 2005 / MAR 2006)

TECH

  • Chilled Water Pipeworks (MAR 2006 / JUN2006)

AFFYMETRIX

  • Hook up piping work for DI and Drain, Dicer wafer and wafer washer and Wet Bench Subprep
  • Supply, fabricate & installation of Equipment Foundation (MAY 2000 /SEP 2000)

M+W ZANDER PTE LTD

CSM FAB 7

  • Supply and install steel beam finishing with epoxy paint at Fab. 7 Level 2 Building
  • Installation works for make-up air unit MAU 3-8-2008 (JAN 2009)

AFFYMETRIX

  • Mechanical piping installation for UHP system (FEB 2006 / MAR 2006)
  • DI system (plant room) Mechanical piping installation (FEB 2006 / MAR 2006)

SUNPOWER (MANILA, PHILIPPINES)

  • Supply of mechanical piping skids for UPW plant (MAY 2007)

SEAGATE JOHOR

  • Phase 2 – Mechanical Piping installation for Seagate J1 PH2 RODI Plant (SEP 2008)
  • Phase 1 – RO Plant (DEC 2007)

SEAGATE W3

  • Mechanical piping installation for UPW plant (ON-GOING)

CSP – WOODLANDS

  • Supply & install additional process cooling water system in CSP Fab. 6 (Phase 3) (OCT2002 / FEB 2003)

SILTERRA – PEMBINAAN

  • Supply, fabricate & installation of Equipment Foundation (MAY 2000 /SEP 2000)

STM AMK 6 – EXPANSION

  • Proposed extension / Retrofit of existing building at A.M.K. for ST Micro (STM AMK6E)
  • Waste water collection system (FEB 2004 / JUN 2004)
  • Supply & install for compressed dry air system (F-21, Bulk Gas System) (APR 2004 / MAY 2004)
  • Process drain system & additional FAR Sump & tank complete with piping works (FEB 2005 / JUN 2005)
  • Stainless steel plate foundation for Equipment ID IHV-07, IHC-09, IHC-10, IMC-03 & IHV-08.

M+W ZANDER PTE LTD

SILTRONICS

  • F25B – Process Drains (DEC 2007)
  • F45B – Process Water Plant Piping Works (2010)

IMFS FAB 10N (PACKAGE: F08)

  • Project: S6598 (S-6624) F08A & F08B – Central Mechanical Plant Installations (SEP 2008)
  • Hibernating of Hot Water and Heat Recovery Water Systems (2010)

PHILIP MORRIS

  • F24, Potable Water Treatment Plant Piping (2011)

METALLKRAFT

  • F08A, Process piping installation for Slurry Recovery Building (2011)

ON-GOING WORKS (as Yenn Dar Pte Ltd is the nominated sub-contractor)

  • Supply and install, modify and replacement exhaust ducting for Machine.
  • Supply & install of CTW Line for DI water and W5 line replacement.
  • Supply and install CDA, PV, GEX, PCWS, PCWR and RD-2 process piping and exhaust line.
  • Supply and install chilled water pipe with insulation and mounting of dry coil.

ROCHE

  • F02, HVAC (2013)
  • F08A, Mechanical System (2013)
  • F06C, Sampling Room (2013)
  • F02A, Ductworks & piping (2013)

M+W ZANDER PTE LTD

MICRON FAB 10 EXTENSION (FAB 10X)

  • DDU Dalian Intel Site – HK24 High Vacuum – Material Supply and Delivery (Ongoing)

MICRON FAB 10 EXTENSION (FAB 10X)

  • F08A – Chilled Water Pipework and Accessories Diesel Fuel Oil Pipework and Natural Gas – CUP (Ongoing)
  • F08B – Chilled Water Pipework and Accessories and Natural Gas – FAB and Miscellaneous (Ongoing)
  • C42A/B – Plumbing and Sanitary for CUP and FAB Building / ADMIN Building (Ongoing)

METALLKRAFT

METALLKRAFT AT TUAS SOUTH AVENUE 14, 1D

  • Demolishing of pipeworks, tanks, equipment and electrical for Areas 1 to 10 (Ongoing)

LAB AT WOODLANDS 11

  • Dismantling of existing furniture & fixtures, air-con, false ceiling, flooring at front office, lab equipment area, etc. (Ongoing)

TAKASAGO THERMAL ENGINEERING CO., LTD / TAKASAGO SINGAPORE P/L

CSM FAB 3 – WOODLANDS

  • Process Cooling Water Expansion in CUB Fab. 3 (NOV 2000 / FEB 2001)

SINGAPORE BIOTECH FACILITY – 60 TUAS WEST DRIVE

  • Instrument Air Distribution
  • Low Pressure hot water S&R
  • Low Pressure Condensate & low pressure steam
  • Outside Building – Cooling Tower Package (SCHERING PLOUGH PROJECT) (JUL 2001 / OCT 2001)

NEPES

  • Supply and Install piping for Chilled Water, Process Cooling Water, CDA, N2 and PV systems (DEC 2005 / FEB 2006)
  • Supply and Install Utilities Hook Up for 2006 Machine (DEC 2005 / FEB 2006)
  • Plating 12″ (No.3) hook up (MAY 2006)

ASP

  • Cooling Tower upgrading works – Steel structure work & modification of condenser water pipe (AUG 2006)
  • Supply and install pipe racks for the new layout at NOX (APR 2007)

CSM FAB 7

  • Supply and install pipe and fittings for cooling tower are, chiller water #3, MAU/F/3-7, Process Vacuum System,
  • Process Water System, PCW, Heat Exchanger (SEP 2006)
  • Supply & install carbon steel pipe and fittings at Chilled Water 5 Deg & 11 Deg, eye-shower at support area (SEP 2006)

CSM FAB 7C EXPANSION

  • Piping works for TMAH & H202 room (AUG 2008)

GENENTECH

  • Utility piping (Mechanical Package) (SEP 2008)

REC SINGAPORE

  • Underground utility services (DEC 2009)
  • Metalkraft piping works (2010)
  • Maintenance support services (2013)

TAKASAGO THERMAL ENGINEERING CO., LTD / TAKASAGO SINGAPORE P/L

HOYA

  • Supply & install Utility loop CDA & PCW piping works (JUNE 2012)

REC CAPEX MODULE C3

  • Supply & install process exhaust and process piping for new cell (2011)

AMGEN

  • Utility Piping & Additional works (2014)

NOVARTIS

  • Mechanical Piping & underground fire water retention piping (2015)

NOVARITS ME III

  • Supply & install of piping (2015)

TAIKISHA SINGAPORE PTE LTD

SGH

  • Supply & install Laboratory Exhaust SS304 Ducting for ACMV System (2013)
  • Supply & install Laboratory Exhaust SS304 Ducting for PIG & SPF holding room, Mock-up (2012)

BREADTALK

  • Proposed fitting out works at 5th & 6th Storey at new HQ building to Breadtalk Group at Paya Lebar I-park (2013)

MDC at NTU

  • Structure Steel works (2013)

MDC at MYANMAR

  • Structure Steel works & Fit out works (2014)

ABBVIE

  • Additional gas piping for Bio Lab and Condensate drain for MAU at New Canteen Area(Ongoing)
  • Pipe, platform, etc work for cooling tower (Ongoing)
  • Dismantling work & additional chilled water pipe connection (VO Additional) for cafeteria (Ongoing)

PURETECH PTE LTD

JURONG SHIPYARD PTE LTD

    • Supply & installation of pipe works (workshop, warehouse & ancillary building for shipyard development (2013)

BULOX POWER PTE LTD

LTA LINE – CONTRACT #T206, POWERGRID APPROVED 22KV CONTAINERIZED
SUBSTATION

  • Supply & install Containerized Substation and transformer yard (2016)

LTA LINE – CONTRACT #T207, POWERGRID APPROVED 22KV CONTAINERIZED
SUBSTATION

  • Supply & install Containerized Substation and transformer yard (2016)

LTA LINE – CONTRACT #T217, POWERGRID APPROVED 22KV CONTAINERIZED
SUBSTATION

  • Supply & install Containerized Substation and transformer yard (2016)

LTA LINE – CONTRACT #T206, ELECTRICAL INSTALLATION WORK TO TEMPORARY
SUBSTATION

  • Supply, install, management and coordination for the electrical works (2016)

GE INFRASTRUCTURE WATER & PROCESS TECHNOLOGIES

MICRON FAB10X 750 EXPANSION – INSTALLATION AND COMMISSIONING SUPPORT

  • Mechanical Scope – CUP (Ongoing)